Exterior from east corner |
![]() |
Underpinning is proceeding smoothly; the second sequence of panels should be poured by the end of the day. |
![]() |
Excavation of new entertainment space is approximately 80% complete |
Drywall is being hung and taped; the new kneewall at the stair is partially installed |
![]() |
Living room |
![]() |
Chapter room |
![]() |
Kitchen |
Upper Hall |
![]() |
South bathroom: Three new showers in place |
![]() |
North Bathroom: Two new showers in place |
Attic: New supply ductwork for second floor bedrooms |
![]() |
Existing basement / future mechanical room; new electrical panels in place |
New stair / passageway from existing basement to entertainment room; note the 5 gallon buckets |
Excavation progress of new toilet room under living room. All interior excavation is being done by hand. |