Sunday, December 30, 2012

Exterior Progress


Additional handrail at top of seating area
Additional handrail at perimeter of patio

Guardrail / handrail complete
Site signage in place

Monday, December 3, 2012

OAC 15: Getting close!

New entrance at Preston Place / progress on the exterior cornice paint prep
South Addition; grading at patio underway
South Elevation with curb cut prepartion
East elevation with asphalt in place on driveway
Party room entrance / patio access stair; progress on the amphitheater seating at sunken courtyard
Exterior stair outside of Party Room entrance
Party room interior (at sunken courtyard entrance)
Party room from bar
Willie Alexander Room / Dining; progress on the sliding doors into Chapter room
View of patio from Roof Deck (outside of Willie Alexander Room)
East Addition - Second floor hallway with wood floor
South bedroom (facing Grady Ave / sunken courtyard) 



Friday, November 16, 2012

OAC 14: Exterior concrete / drywall progress

South elevation (from Grady Ave)
Concrete stairs down to sunken courtyard and up to patio
Amphitheater seating currently being formed / poured
Looking south (to Grady from ground floor porch)
Ground floor porch over entertainment room extension

Porous concrete poured at north parking area
Entertainment room (looking south to sunken courtyard) interior
Dining room (looking south to porch) interior
South porch interior

Friday, November 2, 2012

OAC 13: Window Installation!



Progress from Grady Ave; framing for both additions is complete
New south porch addition with windows installed
Concrete formwork in place for the new sunken courtyard and amphitheater seating
Looking east into the sunken courtard and future stairs to the east parking area
Concrete for porch in place
North parking area with gravel in place; porous concrete for the parking area will be poured in the upcoming week.  Note, the HVAC condensing unit will be relocated and the curb continued
Party room interior; most of the electrical and plumbing rough-in work is complete
Party room bar (at north end of room)
Dining Room looking south to porch
Second floor hallway; purple temporary wall will be removed and open to the Grand Foyer / existing stair
South bedroom in the east addition

Sunday, October 21, 2012

OAC Meeting 12 - South addition takes shape

Framing starts to take shape on the South Addition
Second floor framing of east addition is compete and windows have been installed
The south porch takes shape; the new at-grade patio will be approximately 18" below the porch finished floor
Curbing has been installed along house

=