OAC 13: Window Installation!



Progress from Grady Ave; framing for both additions is complete
New south porch addition with windows installed
Concrete formwork in place for the new sunken courtyard and amphitheater seating
Looking east into the sunken courtard and future stairs to the east parking area
Concrete for porch in place
North parking area with gravel in place; porous concrete for the parking area will be poured in the upcoming week.  Note, the HVAC condensing unit will be relocated and the curb continued
Party room interior; most of the electrical and plumbing rough-in work is complete
Party room bar (at north end of room)
Dining Room looking south to porch
Second floor hallway; purple temporary wall will be removed and open to the Grand Foyer / existing stair
South bedroom in the east addition