Progress from Grady Ave; framing for both additions is complete |
New south porch addition with windows installed |
Concrete formwork in place for the new sunken courtyard and amphitheater seating |
Looking east into the sunken courtard and future stairs to the east parking area |
Concrete for porch in place |
North parking area with gravel in place; porous concrete for the parking area will be poured in the upcoming week. Note, the HVAC condensing unit will be relocated and the curb continued |
Party room interior; most of the electrical and plumbing rough-in work is complete |
Party room bar (at north end of room) |
Dining Room looking south to porch |
Second floor hallway; purple temporary wall will be removed and open to the Grand Foyer / existing stair |
South bedroom in the east addition |