| Exterior looking north; site is a major mudpit right now |
![]() |
| Future east wall of basement party room with new opening to basement men's toilet room and basement |
| Trench for new water and fire lines |
| Exterior at Preston Place; new foundation drain to be added and waterproofing applied to existing concrete foundation wall |
| New opening from party room into women's toilet |
![]() |
| Living room awaiting interior paint |
![]() |
| Chapter room awaiting interior paint (not paint swatch in image is not final color) |
![]() |
| Kitchen with new quarry tile floor, awaiting interior paint |
| New full bath under stairs with tile and painting complete |
| Arches restored on the second floor at grand foyer |
![]() |
| Bedroom 1 with first coat of paint |
![]() |
| Bedroom 5 with first coat of paint |
![]() |
| Bedroom 2 with first coat of paint |
![]() |
| Bedroom 3 with first coat of paint |
![]() |
| South second floor bathroom with shower installed and first coat of paint |
![]() |
| Former crawlspace / future men's & women's basement toilet rooms |