Friday, November 16, 2012

OAC 14: Exterior concrete / drywall progress

South elevation (from Grady Ave)
Concrete stairs down to sunken courtyard and up to patio
Amphitheater seating currently being formed / poured
Looking south (to Grady from ground floor porch)
Ground floor porch over entertainment room extension

Porous concrete poured at north parking area
Entertainment room (looking south to sunken courtyard) interior
Dining room (looking south to porch) interior
South porch interior

Friday, November 2, 2012

OAC 13: Window Installation!



Progress from Grady Ave; framing for both additions is complete
New south porch addition with windows installed
Concrete formwork in place for the new sunken courtyard and amphitheater seating
Looking east into the sunken courtard and future stairs to the east parking area
Concrete for porch in place
North parking area with gravel in place; porous concrete for the parking area will be poured in the upcoming week.  Note, the HVAC condensing unit will be relocated and the curb continued
Party room interior; most of the electrical and plumbing rough-in work is complete
Party room bar (at north end of room)
Dining Room looking south to porch
Second floor hallway; purple temporary wall will be removed and open to the Grand Foyer / existing stair
South bedroom in the east addition

Sunday, October 21, 2012

OAC Meeting 12 - South addition takes shape

Framing starts to take shape on the South Addition
Second floor framing of east addition is compete and windows have been installed
The south porch takes shape; the new at-grade patio will be approximately 18" below the porch finished floor
Curbing has been installed along house

=

Tuesday, October 2, 2012

OAC Meeting 11 - Framing Progress


View from Grady: Ground floor mixed use room is framed; second floor joists are in place

Porch: Looking east towards Pi Phi over party room extension

Mixed Use: Looking south (towards Grady Ave); large opening will have outswing french doors to porch
Mixed Use: Looking north (towards Sigma Chi); doorway to stair beyond
Party Room: Looking north (towards bar area) with door to storage under stairs
Party Room: Looking south (toward courtyard); large opening to receive outswing french doors
Second Floor: New entrance to Grand Foyer currently infilled with fire rated wall to separate Phase 1 / Phase 2







Friday, September 21, 2012

OAC Meeting 10: East Addition progress

Ground floor walls of east addition are complete; waterproofing has been applied and the ground floor joists have been placed.
Steel decking will be covered with concrete for the portion of the porch that is over enclosed space
Interior of new entertainment room; underslab plumbing to be installed shortly.  
Inside the entertainment room (looking south) to new doors leading out to future sunken courtyard.  Doorway on the right will lead to the existing basement and men's toilet room.
New men's and women's toilet rooms with slab in place






Friday, August 31, 2012

OAC Meeting 9: Coming out of the ground!

Temporary mulch in the front yard to accommodate events
Future curb cut along Grady Ave
New entrance to basement party room in place
The east addition takes shape
Future patio
Interior of party room (looking north)
Interior of party room (looking south)
Future men's and women's toilet rooms in the basement (below the living room)

Friday, August 17, 2012

OAC Meeting 8: Phase 1 Complete / Punchlist

Looking south with the new masonry screen wall in the foreground (it doubles as brick mockup for the new additions)
Foundations have been poured for the new east addition
Looking north in the future party room
View from the front door

Chapter room with lockable closet for audio visual equipment
Kitchen with last minute shelf and counter installation
Grand foyer with restored archways

The new drop down stair to the attic
Second floor bathroom (south)




Second floor bathroom (north)
Attic with new ductwork for heating and cooling
Basement with final adjustments to the fire alarm system
New stair from basement to party room