O/A/C Meeting 4: Rough-in / Excavation Progress

Demolition of the existing east addition, including foundation is complete.  Site subcontractor is fully mobilized and started footing / underpinning excavation on Friday.
Removal of existing porch and demolition of deck and patio are complete; existing columns are in Contractor's shop and will be re-installed with the new south addition is complete.
Existing east elevation with all windows removed
Entrance hallway; new recessed light fixtures and fire sprinkler system have been roughed in.  The new stairway kneewall is complete.
Living room with new lighting / fire sprinkler / ceiling speaker wiring roughed in.
Kitchen with all electrical roughed in; additional plumbing rough in for  kitchen sink at window and floor drain on track for the upcoming week
Grand foyer with full-height wall removed and arched openings to remain.
An embedded railroad track, which supported the large window at the top of the stairs.
New south bathroom with showers roughed in.
Attic mechanical room with one AHU set in place and ductwork installed throughout to serve second floor bedrooms.
Basement / new laundry room.  Existing door and window will be reused as openings for ductwork into addition
Existing crawlspace / future toilet rooms to serve the basement level entertainment space.