| Exterior from east corner |
![]() |
| Underpinning is proceeding smoothly; the second sequence of panels should be poured by the end of the day. |
![]() |
| Excavation of new entertainment space is approximately 80% complete |
| Drywall is being hung and taped; the new kneewall at the stair is partially installed |
![]() |
| Living room |
![]() |
| Chapter room |
![]() |
| Kitchen |
| Upper Hall |
![]() |
| South bathroom: Three new showers in place |
![]() |
| North Bathroom: Two new showers in place |
| Attic: New supply ductwork for second floor bedrooms |
![]() |
| Existing basement / future mechanical room; new electrical panels in place |
| New stair / passageway from existing basement to entertainment room; note the 5 gallon buckets |
| Excavation progress of new toilet room under living room. All interior excavation is being done by hand. |